Headlines:

Greater Accra

NO. REGION PROJECT LENGTH (km)
    RESEALING  
1 GAR Resealing of Adenta-Agomeda Road (km 0-8) 8.0
2 GAR Resealing of Adenta-Agomeda Road (km 8-16) 8.0
3 GAR Resealing of Adenta-Agomeda Road (km 16-23) 7.0
3     23.0
    CONSTRUCTION/REHABILITATION  
1 GAR Selected Roads within Greater Accra (11.95km) 11.95
1     11.95
    SECTIONAL REPAIRS/PARTIAL RECONSTRUCTION/ASPHALTIC OVERLAY  
1 GAR Partial Reconstruction/ Asphaltic Overlay on Kasseh - Ada Road (20.7km) - Lot 2 20.7
2 GAR Sectional Repairs and Overlay on Michael Camp-Afienya-Doryumu Town (18.5km) and Speed Tables at Korledor on N1 18.5
2     39.20
    REHABILITATION (PAVED)  
1 GAR Rehabilitation of Afienya-Dodowa Road (km 0.0-15.3) 15.3
2 GAR Rehabilitation of Afienya-Dawhenya Road (7.2km) 7.2
3 GAR Rehabilitation of Ayikuma-Doryumu Road (10.8km) 10.8
4 GAR REHABILITATION OF SELECTED ROADS IN GREATER ACCRA (30.5km) (Dome-Kitase Road (14.8Km) Ashongman, Haatso & Agbogba Estate Roads (2.2km) 17.0
4     50.3
    UPGRADING  
1 GAR Prampram-Anyaman Road (Latsinyo-Anyaman Road) 10km Lot 1 10.0
2 GAR Oyibi -Ashaiman Road (km 0-11.7) 11.7
3 GAR Adjeikojo-Ashalley Botwe Road (10.5km) 10.5
3     32.20